The renovations at the Brothers St Brendan’s Rugby League Club have been progressing well! Here are What’s been done since 11 December 2023:
 
Works undertaken 11/12/2023 – 12/01/2024
• Completed set up of exterior scaffold
• Completed level one joist rectification and floor openings for the lift and stairs
• Continued bricklaying to level one window openings
• Commenced saw cutting of ground floor slabs for future plumbing
 
Works undertaken 15/01/2024 – 26/01/2024
• Completed bricklaying to level one window openings.
• Completed saw cutting of ground floor slabs for plumbing.
• Commenced ground level plumbing.
• Commenced level one partition walls framing.
 
Works undertaken 29/01/2024 – 09/02/2024
• Completed level one partition walls framing.
• Completed level one ceiling framing.
• Completed ground level in ground plumbing rough in.
• Commenced installation of air-conditioning ducting.