The renovations at the Brothers St Brendan’s Rugby League Club have been progressing well! Here are some shots of the progress since 25 March 2024.
Works undertaken in previous period (25/03/2024 – 05/04/2024)
  • Commence tiling of wet areas on level one
  • Commence ground floor fire rated ceiling works
  • Commence preparations for footings for external stairs and hydrants
Works planned for next period (08/04/2024 – 19/04/2024)
  • Continue tiling of wet areas on level 1
  • Continue ground floor fire rated ceiling works
  • Continue external stair and hydrant works
  • Commence floor preparations to level 1 function space and terrace
  • Commence electrical rough-in and switchboard installation to level 1