The renovations at the Brothers St Brendan’s Rugby League Club have been progressing well! Here are some shots of the progress since 26 Feb 2024.
Works undertaken in previous period (26/02/2024 -08/03/2024)
• Level one ceiling sheeted.
• Level one wall framing installed.
• Level one wall sheeting underway.
• Ground floor blockwork in progress
Works planned for next period (11/03/2024 – 22/03/2024)
• Continue setting and sanding the level one ceiling
• Commence waterproofing level one wet areas
• Commence installation of doors
• Excavation for fire hydrant line