The renovations at the Brothers St Brendan’s Rugby League Club have been progressing well! Here are some shots of the progress since 7 May 2024.
 
Works undertaken in previous period (07/05/2024 – 17/05/2024):
• Complete waterproofing to ground floor amenities
• Commence tiling of ground floor amenities
• Commence preparation and pouring of external concrete pathways
• Continue installation of external stairs and canopy roofs
• Continue external inground hydraulic services and connections
 
Works planned for next period (20/05/2024 – 31/05/2024):
• Commence construction of internal stairs
• Commence painting of ground floor walls
• Commence laying of external blockwork walls
• Commence construction of external seating
• Continue tiling to ground floor amenities
• Continue pouring external concrete pathways
• Continue external inground hydraulic services and connections