The renovations at the Brothers St Brendan’s Rugby League Club have been progressing well! Here are some shots of the progress since 8 April 2024.
 
Works undertaken in previous period (08/04/2024 – 19/04/2024)
• Tiling of wet areas on level 1
• Electrical rough-in on level 1
• Ground floor fire rated ceiling works underway
• Preparatory works for installation of the lift
• Continuing external sewage and stormwater works
 
Works planned for next period (22/04/2024 – 3/05/2024)
• Installation of lift structure and lift carriage
• Installation of the locks to level 1 doors
• Installation of ground floor steel structure for the external stairs
• Ground floor civil works
• Waterproofing to ground level toilets